|
|
Event |
Description |
Cost |
|

|
1 |
The
extrusion department makes 100 pounds of C-80019 extrusion that is
defective. One flange is bent slightly inward. The defect is not detected.
At this point, the extrusion has cost $1.16/lb. |
$116.00 |
|

|
2 |
The
extrusion moves through several additional processes including paint. It
is stored, handled, and records are kept. The additional cost is $0.19/lb. |
$ 19.00 |
|
|
3 |
An
operator sets up a punch press to notch the ends. The setup requires 0.5
Hours @ $11.75/Hr. |
$ 5.88 |
|

|
4 |
An
operator attempts to notch the extrusions. The bent flange prevents entry
into the punch die. The operator calls for a supervisor and waits for 15
minutes. Operator cost is $11.75/hour. |
$ 2.94 |
|

|
5 |
Supervisor
arrives. Operator and supervisor attempt to process the parts without
success. Supervisor calls Diemaker. Both wait for arrival of
diemaker. Total time is 20 minutes. Supervisor's time costs $14.75/hour. |
$ 8.75 |
|

|
6 |
Supervisor,
Operator, and Diemaker discuss the problem and attempt to process without
success. They decide to grind out the die so the extrusion with the bent
flange will fit into it. All three work to remove the die and take
it to the die shop. Total time required is 1.0 Hours. Diemaker's cost is
$13.50/hour. |
$ 40.00 |
|
|
7 |
Diemaker
grinds out die, returns to press and sets up the press. Total time 3.4
hrs. |
$ 45.90 |
|
 
|
8 |
Diemaker,
Operator, and Supervisor assemble to determine status. The operation seems
to work. Diemaker and Supervisor go on to other activities, Operator
prepares to process parts. Total time required 17.0 minutes. |
$ 11.33 |
|

|
8A |
Scheduler
spends 1.5 Hrs @ $15.75/Hr to change schedule and advise
customers of change. |
$ 23.63 |
|

|
9 |
Operator
processes parts and carries them to the Assembly department. Total time
for the lot of 100-lb of parts is 50.0 minutes. |
$ 9.79 |
|
|
10 |
Assembly
builds windows with the defective parts. Many windows do not operate
properly because of the bent flange. Assemblers expend 4.2 extra man-hrs
attempting to make the windows operate. Assembler time costs $10.50/hr. |
$ 44.10 |
|

|
11 |
An
Inspector notices that some windows are difficult to operate. She confers
with Assembler for 15.0 minutes and decides to summon the inspection
supervisor. Inspector rate is $12.75/Hr and Inspection Supervisor is
$17.25/Hr. |
$ 5.81 |
|

|
12 |
The
Inspection Supervisor arrives and the Assembly Supervisor comes to see
what the problem is. Four persons meet on this problem for 13.0
minutes and decide to summon the Engineer. All wait for
an additional 11.0 minutes until the Engineer arrives. |
$ 21.28 |
|

|
13 |
The
Engineer, Inspection Supervisor, Assembly Supervisor, Assembler, and
Inspector confer for 25.0 minutes and determine a way to fix the problem.
All then depart to other activities. The Engineer's time costs
$26.75/Hr. |
$ 34.27 |
| |
13A |
Inspector
Documents events-- 25 minutes. |
$ 5.31 |
|
|
14 |
Assembler
works for 3.9 hours to repair windows and then sends them to
shipping and eventually to the customer. |
$ 40.95 |
|

|
15 |
After
2 weeks, customer calls. Some of the windows worked OK until they were
installed. Then the bent flanges caused additional problems. Customer
requests a Field Service Engineer to fix the problems. Engineer spends 35
minutes. |
$ 15.60 |
|

|
16 |
After
many phone calls, it is decided to send a Field Service Engineer to the
construction site. Times involved in making this decision:
Engineer.............3.75 Hrs @ $26.75/Hr
QA Supervisor.....1.75 Hrs @ $17.25/Hr
Plant Manager.....1.75 Hrs @ $52.00/Hr
Field Engineer.....1.60 Hrs @ $17.00/Hr |
$248.70 |
|

|
17 |
Field
Service Engineer spends 37.0 Hrs in travel to site, fixing problems, and
reporting. In addition, Engineer spends 1.6 Hrs on the problem. The
Sales Manager spends 3.4 Hrs @ $48.00/Hr. Travel costs $987. |
$1822.00 |
|


|
18 |
Weeks later, the same part
is run again. It is found that the
die can no longer run parts that are in spec because it has been
"relieved" too much. A similar chain of events occurs.
Time required:
Diemaker..........8.0 Hrs
Supervisor........0.5 Hrs
Operator..........2.0 Hrs
Engineer..........0.7 Hrs
Inspector.........0.9 Hrs
|
$169.08 |
| |
|
Scrap
Value @ $0.17/lb |
$ -17.00 |