|

Lean
Manufacturing Case Study
Mechanical
Control Cables
|

Lean
Resources









|
| This
implementation case study is a real
company with real people. For confidentiality, we will
call it "Mechtrol", though that is not their name. When
Mechtrol was founded twenty or thirty years before, it was highly
successful and made large volume orders with limited variety.
Over the years, markets changed and
the product mix became increasingly
varied and with much smaller orders. The increasing
variety demanded increasing overhead in terms of engineering,
material handlers, salespeople, production control, and a host of
other tasks.
The traditional accounting allocations
tended to assign too much overhead cost to high volume
products and not enough to low volume. This had, in
turn, led to more low-volume orders and fewer high-volume orders.
But these effects were so slow in developing that they went
unnoticed.
|
Now,
Mechtrol was in trouble. Profit margins were low and market share
declining. Quality and delivery was not competitive. Two or three
consultants spent the better part of four months at the firm. They
taught, learned, experimented, and cajoled. As
always, paradigm changes are difficult and frustrating
and Mechtrol was no exception.
In
the end, five workcells were in place and a macro layout showed
the locations of remaining cells. Training was well along and
teams were developing. Supervisors were learning to deal with the
cell environment. Mechtrol carried on this work in the years
that followed. The organization had
internalized the lessons and spirit of Lean Manufacturing. |
|
|
Element |
Original
Situation |
Changes |
| Workcells
& Flow Layout |
Products
were built on long, high-speed assembly lines.
Separate sub-assembly areas built up orders of subassemblies prior to
running the order on the line. |
We
identified product families based on commonality of parts and tooling.
Cells were then designed each capable of operating with 1-10 workers. Almost
all operations, including subassembly, are now internal to the
cells. |
| Teams |
An
informal social hierarchy existed in the factory that was largely based on
skills and job classification. At the very top were Tool & Die Makers.
Then came Screw-Machine Operators, Punch Press Operators, Setup Men,
Machine Operators, and Assemblers in that order.
The social structure was
dysfunctional and caused large inefficiencies for a variety of
reasons. |
Teams
were formed for each workcell. They had training in SPC and
problem-solving but not in team processes. Nevertheless, because of the
cell design, the teams quickly bonded and
generally work well together.
Teams
perform setups, Quality Assurance, and Packaging which had previously been
in a different department. |
| Lean
Scheduling |
Scheduling
was done on an MRP system that was so old there was no longer software
support. Moreover, the system was not trusted due
to a lack of data integrity and general performance. |
Initially,
the MRP system was simply bypassed. Kanban
stockpoints were set up for repetitive components. Some
repetitive end-products used a Kanban stockpoint in Finished Goods. Low
volume or intermittent products were built to order.
Several
years later, the MRP system was replaced. Because Mechtrol now had the
experience to know what was needed, the new MRP was very successful. |
| Rapid
Setup |
Setup
operations were casual. Many small presses and machines had to be setup
and then all of them arranged along the assembly line before starting a
run. A major line changeover could take all
day.
To minimize major changeovers, orders were
grouped by similarity and had to be run in sequence. This
complicated scheduling, created WIP, excess finished goods and introduced
wide variability into the lead time. |
1)
The workcell configuration limits the number of different fixtures within
a cell and thus reduces the number of setups.
2)
The firm's Tool & Die shop consolidated multiple operations onto a
single die-set for some products. Other modifications speed setups.
3) Cell
workers perform setup operations and have incentives to setup fast. |
| Six
Sigma |
Quality
consisted of a final inspection at the end of each high-speed line. By
the time defects were caught, all of the subassembly work was complete and
many items were in final assembly. Moreover, there were upwards
of 20 people working on the line and stopping it to fix the quality
problems was disastrous for productivity. |
Cell
teams inspect their own work after training in blueprint reading, SPC, and
measurement. Former inspectors audit quality occasionally, setup SPC
charts, and monitor SPC activities. In the first
cell, quality improved by more than 90% within the first few days. |
| 5-S |
The
plant was a mess. WIP and tooling was scattered everywhere.
Aisles were crooked and often blocked. |
Following
the initial re-arrangements, the firm spent
many years organizing work at the detail level. The
disappearance of WIP freed space. Floors are painted, teams clean their
areas every day. This factory looks and feels World-Class. |
Results:
Outstanding In Every Way
- Leadership style was unique in this
project. The company President was a pleasant, civilized, and
thoroughly likeable man. He was determined to transform this company
without the usual firings, demotions, or layoffs. The key to this
firm's paradigm shift was the polite relentlessness of its
President. Eventually, people throughout
the organization realized that they could accomplish the necessary
tasks and solve the problems.
|
- The initial transformation of this
company took place more than ten years ago. Many
firms, after an initial success find it difficult to maintain their
success. In this case a lot of credit goes to the firm's
Plant Manager who continually works the details day in and day out.
At any time a dozen or more improvement projects are moving forward.
Continually, relentlessly, over the years the results have
accumulated. This is the true meaning of "continuous
improvement."
|
|